2023 Woodcreek Roads Project - Resident Information

** OFFICIAL CITY OF WOODCREEK NOTIFICATION **

Dear Neighbors, 

Alpha Paving has placed an electronic  "Roadwork" sign at the entrance to the City of Woodcreek, at RR12 and Woodcreek Drive.
The dates for road construction listed on the sign are:   09/11/2023 - 10-11/2023 

From September 11 - September 19, Alpha will ONLY be perform street patching throughout the City.
"Street Patching" involves the contractor removing eight(8) inches or less of asphalt to remove previously existing potholes and other road damage.

Actual paving work will not begin until September 20th.

A Paving Calendar has been created for City Staff by Alpha Paving and is listed under "Supporting Documents" at the bottom of this page.
The Paving Calendar divides the City into 11 Phases of work within the City and is subject to delay, due to weather.

PHASE 1:
   Cypress Point
   Par Circle
PHASE 2:
   Doolittle Drive
   Jack Miller Drive
   Wildwood Circle
PHASE 3:
   Country Lane
   Country Court
   Augusta Lane 
PHASE 4:
   Augusta Drive
PHASE 5:
   Shady Grove Lane
   Brookside Drive
   Elmbrook Drive
   Overbrook Court
PHASE 6:
   Westwood Drive
   Pebblebrook Lane
PHASE 7:
   Brookmeadow Drive
PHASE 8:
   Stonehouse Circle
   Par View Drive
   McGregor Circle
   Spalding Circle
   Wilson Circle
PHASE 9:
   Palmer Lane
   Overlook Court
   Overlook Circle
PHASE 10:
   Garrison Trail
   Woodview Court
   Woodridge Circle
   Canyon Circle
   Canyon Creek Drive
PHASE 11:
   Champions Circle
   Champions Court
   Tremont Trace
       

 

PROCESS for RESIDENT NOTIFICATION:
1.   City Staff receives updated Paving Schedule from Alpha Paving. (Subject to Change, Due to Weather Conditions)
2.   City Staff will distribute the schedule via email blasts and social media.
3.   City Staff will place fliers on residents' doors with specific dates before each road will be paved.

 